Gears, Inc and PEI have been involved in the following projects that utilized soil cement totaling over 1,000,000 tons of mixed soil cement since 1989.
Project: | Highway 36 Hazardous Waste Treatment and Storage Facility, Last Chance, CO |
Owner: | Browning Ferris Industries |
Engineer: | MK Engineering |
Construction: | June 1988 - December 1989 |
The project involved 100,000 sy CTB, 100,00 SY RCC for haul roads, access road, parking areas and processing areas. It also included approximately 15,000 cy of soil cement for a sewer lagoon and retention basins. 99% of the work was completed with GEARS, Inc.'s forces. | |
Project: | Raw Water Reservoir and Sludge Lagoons |
Owner: | City of Corpus Christi, TX |
Engineer: | Black and Veatch |
Prime Contractor: | Midwest Construction Company |
Construction: | February - May 1989 |
GEARS, Inc. mixed with their ARAN 280 B plant approximately 75,000 cy of soil cement for pond liners in 2.5 months. | |
Project: | Red Deer Creek Watershed, Site 14 |
Location: | Miami, TX |
Engineer: | US Corps of Engineers |
Prime Contractor: | Dixon Paving |
Construction: | May-89 |
GEARS, Inc. mixed approximately 3,500 cy of soil cement for bank protection. | |
Project: | Stage II Little Snake Diversion Facilities |
Owner: | City of Cheyenne, WY |
Engineer: | Woodward Clyde Consulting Engineers |
Construction: | July 1989 - September 1990 |
This project involved excavation and the processing of the excavated material for soil cement and the building of 32 dams with this material. The project was an extremely environmentally sensitive project in a high altitude remote area of Wyoming. 100% of the project was completed with GEARS, Inc.'s forces. | |
Project: | N. First Avenue Sewer Improvements; Tucson, AZ |
Owner: | Pima County Wastewater Management Department |
Engineer: | Jerry Jones and Associates |
Prime Contractor: | R.E.M. Construction |
Construction: | Apr-90 |
GEARS, Inc. mixed 36,000 tons of soil cement for stabilization. | |
Project: | Westerly Creek Dam, Lowry AFB; Denver, CO |
Owner: | U.S. Air Force |
Engineer: | U.S. Army Corps of Engineers |
Prime Contractor: | Tarco, Inc. |
Construction: | October- November 1990 |
The project consisted of mixing and placing approximately 7,500 cy of soil cement for a cut off trench and bank protection. | |
Project: | Plains Electric Evaporation Pond, Prewitt, NM |
Owner: | Plains Esclante Generating Station |
Engineering: | Gallup Sand and Gravel |
Prime: | Gallup Sand and Gravel |
Construction: | Jun-91 |
Project consisted of mixing soil cement with various % of fly ash for utilization as pond liners | |
Project: | Laughlin, NV Bank Protection |
Owner: | City of Laughlin, NV |
Engineer: | CH2M Hill |
Prime: | Ames Construction |
Construction: | Jun-92 |
The project consisted of mixing 8,600 tons of soil cement in 8 days for bank protection. | |
Project: | West Elk Mine Retaining Wall |
Owner: | Mountain Coal Company |
Engineer: | Envirocon, Inc. |
Construction: | Apr-93 |
Project consisted of mixing 10,000 tons of soil cement for emergency retaining wall. | |
Project: | Florence, AZ |
Owner: | Department of Corrections |
Construction: | May-93 |
Project consisted of mixing 18,000 tons of soil cement. | |
Project: | CSX Intermodal Expansion, Little Ferry, NJ |
Owner: | CSX Railroad |
Construction: | September - November 1994 |
Project consisted of mixing 34,500 tons of soil cement. | |
Project: | Foothills Basin Channel Project |
Owner: | City of Fort Collins, CO |
Construction: | Oct-94 |
Project consisted of mixing and placing 5,000 tons of soil cement for erosion control structures. | |
Project: | ARCO Warm Springs Project, MT |
Owner: | ARCO |
Contractor: | Barnard Construction, Inc. |
Construction: | May-94 |
Project consisted of mixing 27,000 tons of soil cement in 10 days. | |
Project: | North Deer Creek, Shawnee, OK |
Owner: | Soil Conservation Service |
Construction: | March - April 1995 |
Project consists of mixing and placing approximately 50,000 tons of soil cement for erosion control on up stream face of a new dam. | |
Project: | Phoenix, AZ Project |
Owner: | ADOT |
Contractor: | Ames Construction, Inc. |
Construction: | Jul-95 |
Project consisted of mixing 8,000 tons of soil cement. | |
Project: | Loop 202 - Red Mtn. Expressway, Phoenix, AZ |
Owner: | A.D.O.T. |
Contractor: | Ames Construction, Inc. |
Construction: | January 1996 - April 1996 |
137,941 Tons Soil Cement | |
Project: | 52nd Street Channel Project, Phoenix, AZ |
Owner: | City of Phoenix |
Contractor: | Ames Construction, Inc. |
Construction: | Nov-96 |
5,000 CY Soil Cement | |
Project: | San Antonio Arroyo, Albuguerque, NM |
Owner: | AMAFCA |
Engineer: | Bohannan-Huston, Inc. |
Contractor: | RMCI |
Construction: | March - May 1997 |
50,900 Tons Soil Cement | |
Project: | 67th Ave. Bridge @ Skunk Creek, Phoenix, AZ |
Owner: | A.D.O.T. |
Contractor: | Hunter Contracting, Inc. |
Construction: | April & September 1997 |
24,500 Tons Soil Cement | |
Project: | Table Rock & North Saluda Filtration Project, Travelers Rest, SC |
Owner: | Greenville Water System |
Engineer: | Black & Veatch |
Contractor: | Morgan Corporation |
Construction: | May-97 |
3,365 Tons Soil Cement | |
Project: | Artesia Municipal Landfill, Artesia, NM |
Owner: | City of Artesia |
Engineer: | Smith Engineering |
Contractor: | Sema Construction, Inc. |
Construction: | Oct-97 |
13,700 Tons Soil Cement | |
Project: | Calabacillas Arroyo, Albuquerque. NM |
Owner: | AMAFCA |
Engineer: | Wilson & Co |
Contractor: | RMCI / ASI-RCC |
Construction: | March - May 1998 |
65,840 Tons Soil Cement | |
Project: | Brahman Road Channel, Las Cruces, NM |
Owner | Dona Ana Flood Control Commissioner |
Engineer: | Andrews, Asbury, and Roberts |
Contractor: | Cupit & Company, Inc. |
Construction: | September - November 1998 |
52,314 Tons Soil Cement | |
Project: | Cherokee Fly Ash Ponds, Denver. CO |
Owner: | Public Service Company |
Engineer: | Utility Engineers |
Contractor: | McDonald Farms |
Construction: | December 1998 - February 1999 |
18,838 Tons SoiI / Flyash |